Description

Bonna Indonesia supplied cooling water piping solutions to construct the extension of the Lontar Coal Fired Steam Power Plant in Indonesia.

State electricity company PLN has contracted with a consortium of Sumitomo Corporation, Black and Veatch International Company and local contractor PT Suryamitra Surya Perkasa to carry out a coal-fired power plant PLTU Lontar expansion project with a capacity of 315 MW. The project is part of the government’s 35,000 MW ambitious power plant program.

Bonna Indonesia delivered RCCP pipes (ND2400 mm), special fittings and cradles with seismic design for the onshore and above ground cooling water system. The RCCP installer is SSP.

Project pictures

Key facts

Project Name

PLTU Lontar Extension Unit 4

Contractor

Black & Veatch

Construction Year

2017

Location

Tangerang, Indonesia

Settings for cookies

Consolis uses cookies on its website.

A cookie is a small amount of data generated by a website and saved by your web browser. Its purpose is to remember information about you, similar to a preference file created by a software application.

Cookies perform a number of different functions. Some cookies are essential to deliver our Site and services to you. Cookies can be “persistent”, remaining on your device after you have left the Site or can be “session” cookies that are deleted when you close your internet browser. You can use your browser settings to manage your cookie preferences but please note that in doing so, some functionality of the Site might not be available or might not work as effectively.

Read more about cookie statement and privacy notice.